2018 Street Revitalization Project

The Village is scheduled to begin work on segments of 28 streets this year.  Fourteen segments will be reconstructed and fourteen others will be resurfaced.  Click below for a list and map of the street segments to be completed as part of the 2018 project.

2018 Street Revitalization Project List
2018 Street Revitalization Project Map
2018 Concrete Contractor - Additional Apron Work Flyer

Project Update - Week of August 13

Please note changes to the tentative start dates on all remaining streets listed in the Project Update below.

Abbey Wood Drive (Kensington Lane to Governors Lane):  Asphalt surface placement is tentatively scheduled to occur on Monday, August 13th.  Please avoid parking any vehicles on the street and see “Surface Course” note below under Additional Paving Information listed below regarding Fresh Oil.

Ashley Court:  Concrete work is anticipated to be completed at the beginning of the week. Fine grading is scheduled to occur mid-week followed by asphalt binder installation. Please see “Binder Course” note below under Additional Paving Information listed below.

Bardwick Court:  Concrete removal work is anticipated to start at the beginning of the week, followed by asphalt removal towards the middle of the week.

Castaway Court:  Earth excavation work is expected to be completed during the beginning of the week. Storm sewer work is scheduled to occur mid-week, followed by concrete work at the end of the week.

Claremont Road:  Asphalt surface is anticipated to occur towards the middle of the week.  Please see “Surface Course” note below under Additional Paving Information regarding Fresh Oil.

Essington Court:  Concrete removal work is anticipated to start at the beginning of the week.  Asphalt removal is scheduled to occur mid-week, potentially followed by earth excavation at the end of the week.

Hartford Court:  Concrete work is anticipated to be completed at the beginning of the week. Fine grading is scheduled to occur mid-week followed by asphalt binder installation. Please see “Binder Course” note below under Additional Paving Information listed below.

Westhaven Court:  Earth excavation work is expected to be completed during the beginning of the week. Storm sewer work is scheduled to occur mid-week, followed by concrete work at the end of the week.

 

**Additional Paving Information**
- Binder Course (1st Layer of Asphalt – reconstruction streets only) – Paving signs are placed at the ends of the street on the day prior to asphalt installation.  This layer does not require oil application prior to paving as paving occurs on the stone base.

- Level Binder Course (1st Layer of Asphalt – resurfacing streets only) – Fresh Oil Signs are placed at the ends of the street between 12-24 hours prior to oil application (signs are placed on Friday prior to a Monday morning oil application).  Oil is typically placed in the early morning hours and level binder pavement is placed later that day (all work is weather dependent).  Paving signs are also placed at the ends of the street on the day prior to any asphalt installation.  Any driving on your street after the “Fresh Oil” application will be AT YOUR OWN RISK.  If street access is necessary, driving at less than 10 mph is recommended.  The Village and contractor are NOT responsible for oil on your vehicle when the “Fresh Oil” signs are standing.  This material may track onto your driveway, and/or adhere to your vehicle.

- Surface Course (Final Layer of Asphalt – all streets) - Fresh Oil Signs are placed at the ends of the street between 12-24 hours prior to oil application.  Oil is typically placed in the early morning hours and final surface pavement is placed later that day (all work is weather dependent).  Paving signs are also placed at the ends of the street on the day prior to surface asphalt installation.  Any driving on your street after the “Fresh Oil” application will be AT YOUR OWN RISK.  If street access is necessary, driving at less than 10 mph is recommended.  The Village and contractor are NOT responsible for oil on your vehicle when the “Fresh Oil” signs are standing.  This material may track onto your driveway, and/or adhere to your vehicle.

 

Remember cell phone use is prohibited in construction work zones and as always, please proceed with caution while driving in work zones.

If you have any questions about this project, or if you would like to be added to the list to receive weekly project updates, please email roadconstruction@hoffmanestates.org with the words "2018 Street Project" in the subject line, or call the Transportation and Engineering Division at 847-252-5800.

Free viewers are required for some of the attached documents.
They can be downloaded by clicking on the icons below.

Acrobat Reader Flash Player Windows Media Player Microsoft Silverlight Word Viewer Excel Viewer PowerPoint Viewer